RINK CLOSURE

ON 31ST AUGUST 2022, AT 6.30 PM

CANTERBURY OLYMPIC ICE RINK

WAS CLOSED UNTIL FURTHER NOTICE

WHILST URGENT REPAIRS ARE UNDERTAKEN TO THE ROOF


SEE LATEST UPDATES BELOW


Update: 28th September 2024 – Issued by the Board of the Ice Skating Club New South Wales (ISCNSW)

Just a quick update on the status of our Development Application submitted to Canterbury Bankstown Council in August.  The DA is currently on public exhibition until 8 October 2024 and is accessible to view and comment via the link below.

https://www.planningportal.nsw.gov.au/daex/exhibition/alterations-and-additions-canterbury-olympic-ice-rink

You will be able to view the Architectural Plans and other documentation as submitted, and most importantly under the “Submission” heading you will be able to make a submission/comment on the DA that will be taken into consideration by the Planning team through the review and approval process.  We would of course be grateful for any supportive submissions.

We have sent out an Expression of Interest to a number of suitable construction firms based on these plans, and will evaluate the responses with our Project Manager as they come in over the coming weeks. 

Once Council provides formal questions/responses to our DA we will be in a position to issue the construction tender to the shortlisted firms – the timing of this process remains fluid and we are now only 3 months from Christmas (!!!) so our current estimate is that we will hand over the site to the successful bidder around March/April.  As we receive further information we will continue to share it with you.

The Canterbury Olympic Ice Rink Roof and Amenities Upgrade project is proudly funded by the NSW Government.


Update: April 21st 2024: Current Status – Issued by the Board of the Ice Skating Club New South Wales (ISCNSW)

The Western Sydney Infrastructure Grant (WSIG) Update (formerly West Invest)

Over the past several months, our Project Manager, Andrew Stanton, in conjunction with the Board representatives have been working closely to tender and award each of the key Consultant packages required to produce the documentation required for the approvals process.  The Board has also established a Project Control Group, made up of representatives of the Board and our Project Manager.  This group meets on a monthly basis to discuss general Project Health, Project Status, Objectives, Program, Risks and Opportunities.  Although we have constant communication with our Project Manager, this setting ensures we have positive governance around our Project, enables the project team to raise issues and continue to progress the project forward at a much more rapid rate.

As many may have noticed, Canterbury Aquatic Centre redevelopment has taken full effect next door with demolition works well underway.  The Board has been working very closely with Council Representatives and Public Works officials in “untangling” the two buildings structures, which, has been quite an involved and complex process.  We have worked closely to plan the demolition of the grandstand, which sits over the existing skate hire, while ensuring that this process does not cause the roof of the ice rink to suddenly fail. In planning this process and undertaking design development on the Ice Rink development, we have ensured that the works being undertaken by the Council have positively influenced our design intent.

All major Consultant packages have been awarded and, the Consultant team has been working hard to understand the existing building, its existing condition as well as understand what is required from a compliance perspective to deliver a project of this nature.  The initial Concept Plan which was previously approved by the Board has since been further developed by our Project Architect, Kennedy & Associates, and is progressing well through the design development stage. We are expecting a milestone presentation from our project Architect with developed floor plans, building elevations, details around each of the rooms and finalisation of compliance issues.  This milestone meeting will serve as an opportunity for the Architect and the Board to clarify the overall design objectives and ensure we are moving in the right direction. Pending finalisation of feedback from the board, we anticipate that we will be ready to submit a DA in the two to three months.

The WSIG Program is also maintaining brief web pages for each of the funded projects, and you can find ours HERE.  This will be updated periodically, and as we finalise design and move to DA we look forward to adding some visuals.

PLEASE CHECK BACK AGAIN FOR ANY UPDATES


NSW Government: Canterbury Olympic Ice Rink Roof & Amenities Upgrade Project

Keep up-to-date and get further information on the project by visiting the NSW Government website using the link pasted above.